Brief summary of work completed of white
topping replacing the paver blocks at Hiranandani Meadows
Dr.V.V.Deshmukh (Material
scientist) of the e-Cube consultant takes the pleasure to be associated with
M/S Hiranandani Construction as consultant. The scope of the consultancy was
the replacement of existing interlocking blocks of 125mm height which were laid
at the junctions of concrete road and new road at Hiranandani Meadows with UTWT
(Ultra thin white topping) technology. The story began one year before when then
TMC city engineer Mr.K.D.Lala directed Mr, Cyrus Pithawalla Director
Engineering at Hiranandani construction to me who has first introduced UTWT technology in
thane city and it is now used for the thane city internal roads. The mix design
and construction methodology was provided by me and supervised by e-cub consultant.
The area of around 5000sq.meter has been laid with UTWT. The project started on
10th Jan’ 2015 and completed on 23rd March 2015.
The following areas
were replaced by UTWT’
·
Road from Gemini Tower
to India bulls
·
Road at Junction of T
·
Road at woodrose and Whitefield
·
Road at junction of
north side
·
Road at Hazelnet to
Emrald plaza
The assignment was challenging because though Dr.Deshmukh
has earlier carried out UTWT jobs, the
white topping on WBM (Water bound macadam) was the first of its kind and also
because of our first opportunity to work as consultant to Hiranandani
construction who are one of the bests in quality of construction, design and aesthetics
The methodology of
white topping is as follows
Ø
Remove the existing interlocking
concrete blocks
Ø
Remove the grit powder
used for fixing the concrete blocks
Ø
DBM is .compacted with
the roller and surface is ready for white topping
Ø
Saturate the surface
with water and sprinkle the cement water slurry
Ø
Fix the metal channel
of 125mm height.
Ø
Pour the concrete and
level it with the screed vibrator
Ø
Cut the joints 1meter
by 1metr
The mix design of the
concrete used at Meadows is based on the condition of the road and therefore can-not
be used for another application without consulting us. The concrete is supplied by Lafarge RMC at
G.B.Road Thane.
We have enjoyed working with Mr.Cyrus Pithawalla
and his dedicated team. At Hiranandani Construction the quality checks, the
testing of cubes and documenting of the results are of high standards and hence
unique.
The e-cube consultant
will be always interested to be associated with M/S Hiranandani Construction for
future work.
Dr.V.V.Deshmukh, Material
scientist
Associated with e-Cube